Monday, March 21, 2011

1ST DAY BACK

On our 1st day were told we were starting a new project designed by Rob Shaw.

The project is called : Rob shaw design.

: 14weeks to build it
: LOA is 5.5m,
: Will be using red cedar
: 8mm planking
: Beam is at 2.4m

After the decussion on these details we were given main tasks to do threw the project so we knew who was responsible for each task, which i thought was a great idea. Some tasks were a bit grim compared to others but atleast everyone knew who to go to if question needed to be ansewered.

I was given the task as auto cad man (haha). My job is to get accurate measurements and design details from Rob Shaws designs and pass the information to the class and if needed to add extra detail to the design if changes were to be made. Im quite happy with my task and looking foward to progressing as a boat builder.